We present to you our successful projects, demonstrating the impact we’ve made across various industries. Our case studies provide in-depth insights into the challenges we’ve tackled and the innovative solutions we’ve delivered. Explore these stories to see how we’ve helped our clients achieve remarkable results.

Project K – Deescalation

The ramp-up of serial production for door trims for a Premium OEM, which was the most important project for the group, was successfully executed. This Greenfield project had an estimated value of 50M – 100M EUR. We provided extensive support, including process establishment, de-escalation, customer communication, crisis management, logistical flow, sampling, and industrialization.

The main issues are as follows:

  • The planning of project was inaccurately estimated.
  • The transfer of documentation from headquarters was not completed.
  • The pre-serial phase was not properly handled.
  • Industrialization was not finished on time with 50% of the shopfloor workforce missing.
  • The above contributors resulted in very short period to postponement of SOP at the OEM customer and difficult ramp up and a complicated relationship with the customer, leading to a high level of escalation.
  • GQ reinforced the original hard-pressed team with 15 white collars (managers and engineers – industrialization, quality, project mgr, logistic, engineering, production) and 5 technicians (shop floor quality) and 20+ blue collars successfully installed within the first 2 weeks following original demand.
  • Highest peak of support: 50+ direct people on support and another 100+ indirect (via partner companies).
  • Management of project departments.
  • The customer received strong support to overcome extremely complex problems when the issue started.
  • The customer received expertise of GQ interim professionals who made good and efficient decisions in a short period of time.
  • GQ interim professionals handled difficult communication with an exceptionally demanding customer.
  • Management of project departments.
  • GQ ran a solution on another similar project in pipeline to avoid the same problems in the pre-serial phase.
  • Over the course of 1 year, GQ interim professionals managed to achieve a de-escalation level and resolve most of the problems.
  • Our customer went from heavy crisis firefighting to standard operational conditions with a happy customer and a smoothly running project.
  • In one year, GQ significantly helped our client out of a very deep crisis, tighten relationships with their biggest customer and to resolve seemingly unsolvable problems.
  • At the same time the customer received support with an ongoing project which did not experience the same issues.

Project S -
Sampling

The customer was launching several new projects simultaneously and required interim help to manage all APQP processes and receive PPAP approvals on time.

Projects: Audi Q7, Audi Q8, Porsche Cayenne, Porsche Cayenne Coupe, Volkswagen Touareg.

1 customer submitted 5 different products at the same time which put an additional strain on ramp-up times.

A team of 5 highly skilled interim APQP engineers resolved the project to obtain Green approval from the final customer. This meant completion within 17 months as originally planned without delays or unexpected complications.

  • No need to hire internal staff for limited project tasks
  • Time and resource saving
  • On time and reliable delivery
  • High satisfaction of high-profile OEM

Very precise operation with high performance APQP interim engineers who drove the project through all milestones to the successful PPAP and handover to serial production.

Project R - Relocation of the production line

This project involves the careful transfer of critical manufacturing processes to a new location, ensuring minimal disruption while maximizing productivity and maintaining the highest quality standards.

  • Dismantling in CZ
  • Packing
  • Transportation
  • Assembly
  • Commissioning the line