Quality Management

What is PPAP? The 18 elements and 5 submission levels

PPAP, the production part approval process, is how an automotive supplier proves its series process before deliveries start. Here are the 18 elements, the 5 submission levels, how customers approve a package, why it gets rejected and how VDA 2 compares.

FG
Filip Gergely
19 min read
Supplier quality engineer checking part documents for a PPAP submission at an automotive production line

PPAP stands for production part approval process. It is the evidence package an automotive supplier submits to prove that its series process makes parts that meet every drawing and specification requirement at the quoted rate. The package has 18 elements, a part submission warrant summarizes it, and the customer sets one of 5 submission levels.

The method comes from the Automotive Industry Action Group, AIAG, whose PPAP manual describes it as the industry standard for showing that engineering design record and specification requirements are consistently met. Measurement systems and control plans, both part of the package, are also frequent topics of certification audit findings. In the IATF rolling 12-month data published in September 2026, the IATF 16949 clause on measurement systems analysis caused 3.31% of all major nonconformities and the clause on the control plan 3.02%. This guide explains each element, the levels, how customers approve a submission and why packages come back rejected.

Key takeaways
  • The package is the proof at the end of product and process validation: records from a significant production run show the process makes good parts at rate.
  • The package has 18 elements, from the design record to the part submission warrant, or PSW. Not every element applies to every part.
  • Level 3 is the default: the PSW, product samples and complete supporting data go to the customer, unless the customer names another level.
  • German customers use VDA Volume 2, the PPA procedure, instead, which dropped submission levels in 2020 and became risk-based in its 2026 edition.
72h
From your request to the right GQ interim expert on site Source: GQ interim 2026 brochure

What is PPAP?

PPAP, the production part approval process, is a standard set of documents and sample parts that a supplier submits to its customer before series deliveries start. It answers one question: has the supplier understood every customer requirement, and can its real production process meet those requirements consistently at the planned rate?

The current AIAG manual is the 4th edition. Customers add their own rules on top: Ford’s PPAP requirements effective June 2026, for example, are written for use with the AIAG PPAP 4th edition and the Service PPAP 1st edition. There is no 5th edition of the AIAG manual yet, so customer-specific requirements carry most of the recent changes. A process is approved only when the customer accepts the submission, which is why the approval date is a fixed milestone in every launch plan.

PPAP meaning and full form

The abbreviation stands for production part approval process: the AIAG method in which a supplier proves, with documents and parts from a significant production run, that its series process meets every customer requirement.

When is a PPAP required?

A supplier submits the package for every new part and again whenever something changes that could affect the part. The customer may waive a submission, but the supplier still has to notify the customer and keep the evidence on file. Typical triggers are:

  • a new part or a new supplier for an existing part;
  • an engineering change to the design record, specifications or materials;
  • new, additional, replaced or modified production tooling, including a transfer to another plant;
  • a change of a sub-supplier or of a material source;
  • a change in the manufacturing process or in the operating pattern after approval;
  • production restarting after tooling has been out of use for a long period;
  • correction of a discrepancy found on a part that was already approved.

Customer-specific requirements extend this list. Ford’s 2026 requirements name all new tooled parts, design changes, any change in the supplier operating pattern, any change in the manufacturing process after approval and revised capacity above the verified supplier capacity.

What are the 18 PPAP elements?

The 18 elements are the documents and records that together prove the part and the process. Elements 1 to 9 describe the design and the planned process. Elements 10 to 18 are the validation results and the approval itself. The customer decides which elements it wants to see; the supplier keeps all of them on file.

PPAP elements 1 to 9: design and process
#ElementWhat the customer expects
1Design recordsThe released drawing and specifications, every characteristic ballooned and numbered, plus the material composition report, usually through IMDS
2Authorized engineering change documentsThe approved change notice for any change not yet shown on the drawing
3Customer engineering approvalEngineering sign-off, for example after a vehicle trial, where the customer asks for it
4Design FMEAOnly if the supplier is responsible for the design: design risks and the actions taken
5Process flow diagramEvery step from receiving to shipping, including inspection and rework, with step numbers
6Process FMEAThe risks of each process step, using the same step numbers as the flow diagram
7Control planHow each product and process characteristic is checked in series production
8Measurement system analysis studiesGauge R&R and attribute studies for the gauges named in the control plan
9Dimensional resultsEvery ballooned characteristic measured on parts from the production run, marked OK or not OK
PPAP elements 10 to 18: validation and approval
#ElementWhat the customer expects
10Records of material and performance test resultsMaterial certificates and the test results for every specification on the drawing, often as a DVP&R
11Initial process studiesCapability, usually Ppk, of the special characteristics from the significant production run
12Qualified laboratory documentationThe scope and accreditation of the labs that ran the tests, typically ISO/IEC 17025 for external labs
13Appearance approval reportOnly for parts with appearance requirements such as color, grain or gloss
14Sample production partsParts from the production run, in the quantity the customer asks for
15Master sampleA part signed off by the supplier and kept as the reference
16Checking aidsPart-specific fixtures and gauges with calibration and dimensional records
17Customer-specific requirementsRecords that show the customer’s own rules are met
18Part submission warrant, PSWThe signed declaration that summarizes the submission, the reason for it and the level

Elements 5, 6 and 7 must tell the same story. Our guide to the PFMEA and control plan shows how to build one from the other, and the DFMEA vs PFMEA comparison explains when element 4 applies.

The special characteristics in the DFMEA must reappear in the PFMEA, the control plan and the dimensional results, with the customer’s symbols. The control plan also changes during the launch: a pre-launch control plan with extra checks covers the validation builds, and the production control plan submitted as element 7 describes series production.

Quality engineer measuring an automotive housing with a digital caliper for the PPAP dimensional results
Dimensional results: every characteristic on the ballooned drawing is measured on parts from the production run and recorded.
PPAP date fixed and the package not ready?
Tell us the part, the customer and the deadline. We come back with supplier quality engineers who have closed approval packages before.
Find your expert

What are the 5 PPAP submission levels?

The 5 submission levels decide how much of the package goes to the customer. Level 1 is the warrant alone, level 3 is the warrant with samples and complete supporting data, and level 5 is a full review at the supplier’s plant. At every level the supplier keeps the complete package on file and must be able to show it.

PPAP levels compared
LevelWhat goes to the customerTypical use
1PSW only, plus an appearance approval report for appearance itemsLow-risk items such as standard or catalog parts and bulk materials
2PSW with product samples and limited supporting dataSimple parts where the customer names the data it wants
3DefaultPSW with product samples and complete supporting dataThe default for new parts unless the customer specifies another level
4PSW and other requirements as defined by the customerA customer-defined set, for example only test results
5PSW with product samples and complete supporting data reviewed at the supplier’s plantSafety-relevant or high-risk parts, where the customer wants to see the process

The practical difference between level 3 and level 5 is where the review happens. At level 3 the customer reviews the documents remotely. At level 5 its supplier quality engineer checks the same documents on site, next to the line, the gauges and the master sample, so gaps between the paper and the real process show up quickly.

How do you prepare a PPAP package?

Preparing the package starts at the quote, not after the production run. Most of the package is output of advanced product quality planning, so the supplier collects it as the project runs and uses the significant production run only for the final measurements, studies and samples.

  1. Confirm the level and the customer rules
    Ask for the submission level, the element list and the customer-specific requirements before the kick-off. Customers publish them on the IATF website or their supplier portals.
  2. Freeze the design record
    Get the released drawing revision and all approved changes. Balloon every characteristic so it can be traced to a measurement.
  3. Align flow, PFMEA and control plan
    Use one set of step numbers and one list of special characteristics across all three documents.
  4. Qualify gauges and labs
    Finish MSA studies for every gauge in the control plan and check the scope of each lab before the tests start.
  5. Run the significant production run
    Use production tooling, operators, materials and rate. Take the parts for dimensional results, capability studies and samples from this run.
  6. Collect sub-supplier approvals
    Get approved part submissions for purchased components and materials, plus accepted IMDS entries.
  7. Review the package internally
    Check every element against the drawing revision and the customer rules before anything is sent.
  8. Sign and submit the PSW
    Complete the warrant with the reason for submission, the level and the part weight, then submit and track the customer decision.

How does the customer approve a PPAP?

The customer reviews the submission and gives one of three statuses: approved, interim approval or rejected. Approved means the supplier may ship series parts. Interim approval allows limited shipments for a set time while open points are closed. Rejected means the submission does not meet the requirements and must be corrected and resubmitted.

Each customer runs this differently. At Ford, interim approval needs an approved engineering or build deviation, and the 2026 Ford requirements make the electronic PSW the default. Stellantis states in its IATF 16949 requirements that it applies the process, requests status A before deliveries without deviation and does not sign the PSW; the supplier reads the verdict in Stellantis’s own system.

Capability is where many submissions stall. Ford sets an acceptance level of Ppk 1.67 or more for initial process capability, calculated from at least 25 subgroups of 5 parts, so 125 measurements spread over at least 300 consecutive parts. Until that data exists, the same Ford document requires 100% inspection or mistake proofing integrated into the process. Our guide to statistical process control explains the indices.

Gauges get the same scrutiny. The Ford requirements ask for gauge R&R by the ANOVA method, reported as a percent of study variation and of tolerance: above 10% of tolerance the gauge may not be acceptable and the risk must be evaluated, and above 30% it is unacceptable.

Submissions are now mostly electronic, but there is no common cloud standard: each customer’s portal sets the format. Ford runs service submissions through its e-PPAP system, and Stellantis publishes its verdict in its own information system.

Approved does not mean finished

Many customers require a safe launch period with extra checks after approval. Stellantis notes that acceptance alone is not enough to exit its proactive containment. Plan the people for that period before the PSW is signed.

Why are PPAP submissions rejected?

Most rejections come from documents that do not match each other or the real process, not from bad parts. A customer reviewer checks the links between the drawing, the measurements and the process documents first, because that is where copied or rushed work shows. The common reasons are:

  • Wrong drawing revision: the PSW, the dimensional results and the design record refer to different revisions.
  • Unmeasured characteristics: notes, standard tolerances or material callouts were not ballooned, so they have no result.
  • Broken linkage: the process flow, PFMEA and control plan use different steps, or a special characteristic is missing from one of them.
  • MSA on the wrong gauge: the study covers a different gauge than the one named in the control plan, or the gauge R&R is not acceptable.
  • Weak capability data: too few parts, data not from the significant production run, or Ppk below the customer target without a containment plan.
  • Unqualified lab or incomplete tests: results from a lab without the right scope, or specifications on the drawing with no test result.
  • Missing sub-supplier approvals: a purchased component or material without its own approved submission or IMDS entry.
  • PSW errors: wrong reason for submission, missing part weight or signatures, or declarations that the results do not support.

Sub-supplier evidence is a growing part of the package. Ford requires tier 1 suppliers to use a production part approval process for their sub-tier suppliers and to include the approved sub-tier submissions with each phase of the PSW. A working supplier quality management process collects those approvals before the launch, not in the last week.

How does PPAP relate to APQP?

APQP is the planning process for the whole launch, and PPAP is its proof at the end of phase 4, product and process validation. The FMEAs, the control plan, the MSA plan and the capability targets are planned in the earlier phases; the approval package collects their results. Our article on APQP phases and deliverables covers the planning side.

What is the German equivalent of PPAP?

The German equivalent is VDA Volume 2, the production process and product approval, or PPA, called PPF in German. Many German customers still call the report EMPB, the initial sample inspection report. The 6th edition of 2020 eliminated submission levels and replaced them with an agreement between supplier and customer on the scope, content and schedule of each approval.

The 7th revised edition, January 2026 goes further: the scope of the procedure now follows the risk level of the product instead of a fixed catalog of deliverables, and an online tool replaces the Excel templates. Its annex maps the VDA deliverables to the AIAG elements, and the VDA states that the German industry is open to aligning both procedures in the long term.

VDA 2 deliverables and their AIAG counterparts (VDA 2, 2026, annex 2)
VDA 2 deliverablePPAP element
0.1 PPA report including self-assessment18 Part submission warrant
1.1 Design FMEA4 Design FMEA
2.1 to 2.3 Process flow chart, process FMEA, control plan5 to 7, the same documents
3.2 Geometry, dimensions9 Dimensional results
4.1 Assurance of special characteristics11 Initial process studies
4.2 Production process capacity, 5.2 PPA status of the supply chainNo direct equivalent

What is the difference between PPAP and first article inspection?

First article inspection under AS9102 is the aerospace check that the first production part matches the design. The AIAG method goes further: it proves that the whole process, including gauges, capability and sub-suppliers, keeps making good parts at rate. Aerospace suppliers that need the full approach use AS9145, which adds advanced planning and production part approval to the sector.

PPAP compared with first article inspection
AspectPPAP, AIAGFAI, AS9102
IndustryAutomotive, also rail and industrialAerospace and defense
ProvesThe series process makes good parts at rateThe first part matches the design
Evidence18 elements, capability and MSA from a production runFull measurement of one representative part, with material and process records
RepeatedAfter changes in design, tooling, process or sub-suppliersAfter changes that affect form, fit or function, or after a production break

How does IATF 16949 cover PPAP?

IATF 16949 does not name the AIAG manual. Clause 8.3.4.4 requires a product and manufacturing approval process that meets the customer’s requirements, and the customer-specific requirements then name the method. The GM customer-specific requirements of October 2025 require the AIAG PPAP manual together with GM 1927 03, and Ford requires its Phased PPAP.

Every OEM publishes these documents on the IATF website. Read them before the quote: they set the format, capability targets and interim approval rules for your part.

What a clean submission looks like

The drawing revision is the same on every page, each ballooned characteristic has a result, the flow, PFMEA and control plan share one numbering, every gauge has a passed MSA and every purchased part has its own approval.

How can an interim supplier quality engineer help?

Launch peaks rarely match headcount. An interim supplier quality or APQP engineer can take over one submission or a whole product family, review the package element by element, run the capability studies with your team, chase sub-supplier approvals and handle the customer review until the part is approved. See our APQP engineer and supplier development engineer services, or an interim quality manager when the whole quality team is short.

GQ interim has delivered 2,560+ projects in manufacturing and industrial companies across Central and Eastern Europe since 2015. Our database holds 7,500+ experts, including supplier quality engineers and launch managers, and we are certified to ISO 9001 and TISAX.

72h
to first profiles
Supplier quality and APQP engineers for your launch
Approval packages, capability studies, sub-supplier approvals and customer reviews. Send us the brief and the right expert is on site within 72 hours.
Find your expert
2,560+
GQ interim projects since 2015 (GQ interim project data, November 2026)
7,500+
Experts in our database (GQ interim 2026 brochure)
240+
Clients in Central and Eastern Europe (GQ interim 2026 brochure)
Are you a quality or production engineer?
Join 7,500+ experts in our database and get offers for interim projects in manufacturing across Europe.
See open projects

Conclusion

The approval package is the customer’s proof that your series process works: 18 elements, a submission level agreed in advance and a warrant that your signature makes binding. Packages pass when the documents describe the real line, the measurements cover every characteristic and the sub-suppliers are approved before the production run. Start the package at the quote, and the approval date stops being a surprise.

Interested in our services?

Get a supplier quality engineer for your launch this week

Tell us the part, the customer and the approval date. We come back with experts who have done this before.

72h
From brief to expert on site

Frequently asked questions

What is the meaning of PPAP?

PPAP stands for production part approval process. It is the AIAG method in which a supplier proves to its customer, with 18 elements of documents, records and sample parts, that its series process makes parts that meet every requirement at the quoted rate.

What are the 5 levels of PPAP?

Level 1 is the part submission warrant only. Level 2 adds product samples and limited supporting data. Level 3 adds samples and complete supporting data and is the default. Level 4 is the warrant plus what the customer defines. Level 5 is the warrant with samples and complete data reviewed at the supplier’s plant.

What are the 18 PPAP documents?

Design records, engineering change documents, customer engineering approval, design FMEA, process flow diagram, process FMEA, control plan, MSA studies, dimensional results, material and performance test results, initial process studies, qualified laboratory documentation, appearance approval report, sample parts, master sample, checking aids, customer-specific requirements and the part submission warrant.

What is a part submission warrant?

The part submission warrant, or PSW, is the one-page declaration that summarizes the submission. The supplier states the reason for the submission, the level, the part weight and that the results meet all requirements, and signs it. The customer records its decision on the warrant or in its own system.

What is the difference between PPAP and APQP?

APQP plans the whole launch in 5 phases. The production part approval is the step at the end of phase 4, where the supplier submits evidence from a significant production run that the process makes good parts.

What is interim PPAP approval?

Interim approval lets a supplier ship a limited quantity or for a limited time while open points are closed, for example a capability study that needs more data. Customers set the conditions; Ford, for example, requires an approved engineering or build deviation.

How long does a PPAP take?

There is no standard duration. If the APQP deliverables are complete, the package mainly waits for the significant production run, the capability data and the lab tests. The customer sets its own review time, and missing sub-supplier approvals are the most common cause of delay.

Is the approval process used outside the automotive industry?

Yes. Rail, agricultural and industrial equipment suppliers use the same elements, and aerospace has its own version in AS9145. Medical device makers follow their own validation rules, but some suppliers adopt the same kind of package for critical components.

FG
Written by
Filip Gergely

Filip Gergely is the founder and CEO of GQsystems, a.s., the company behind the GQ interim brand. He founded it in 2011 in Nitra, Slovakia. GQ interim provides interim managers and engineers to manufacturing companies in Central Europe, mainly in the automotive industry, and has completed 1,550+ projects. You can follow him on LinkedIn: https://www.linkedin.com/in/filipgergely.